5 skilled workers can build a wall in 20 days; 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled. 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?

A.
20 days
B.
18 days
C.
16 days
D.
15 days

Solution:

GIVEN:Time taken by 5 skilled workers to build the wall = 20 daysTime taken by 8 semi-skilled workers to build the wall = 25 daysTime taken by 10 unskilled workers to build the wall = 30 daysCalculation:Time taken by 2 skilled workers to build the wall = 20 × 5/2 days = 50 daysTime taken by 6 semi-skilled workers to build the wall = 25 × 8/6 days = 200/6 daysTime taken by 5 unskilled workers to build the wall = 30 × 10/5 days = 60 days Time taken by the three working together = \( {{1} \over {1\over50}+{6\over200}+{1\over60}}\) = 1/(1/15)Time taken by the three working together = 15 days

For more questions,

Click Here

Download Gyanm App

free current affairs for competitive exams

Scan QR code to download our App for
more exam-oriented questions

free current affairs for competitive exams

OR
To get link to download app

Thank you! Your submission has been received. You will get the pdf soon. Call us if you have any question: 9117343434
Oops! Something went wrong while submitting the form.