It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?

A.
3 days
B.
5 days
C.
10 days
D.
13 days

Solution:

Concept:52 men can Complete the work in 10 days. Since 12 men were sent out.Remaining men left = 52 “ 12 = 40We know \(M_1D_1 = M_2D_2\) where, M = No. of Men, D = No. of DaysCalculation:Given:\(M_1\) = 52, \(D_1\) = 10, \(M_2\) = 40Let \(D_2\) = x = ?Now, x can be given by :\(M_1D_1 = M_2D_2\)52 × 10 = 40 × (x)x = \(\frac {52 \: \times \:10}{40} \)= 13? Total number of Days taken = 13 days i.e. 3 Days more than the original estimate.So, Option(1) is the Correct Answer.

For more questions,

Click Here

Download Gyanm App

free current affairs for competitive exams

Scan QR code to download our App for
more exam-oriented questions

free current affairs for competitive exams

OR
To get link to download app

Thank you! Your submission has been received. You will get the pdf soon. Call us if you have any question: 9117343434
Oops! Something went wrong while submitting the form.